PUBLIC REALM UPDATE: Commercial District
The Dale Street work is continuing between Vernon Street and Cheapside with the temporary road closure of Cheapside and Hockenhall Alley allowing the construction of new raised sections of footpath across the side roads along Dale Street.
During this closure, access into Cheapside and Cunliffe Street will still be via Tithebarn Street but egress will be unavailable onto Dale Street making the streets temporarily two-way.
The work area will then move in sections towards Hatton Garden before moving back along the opposite side of the road. The slip road from Hatton Garden will be temporarily closed to allow the safe construction of the kerbs and footpaths.
Delays are continuing to be experienced due to shallow underground services found on site but the City Council is working with partners to undertake diversion works to minimise delays to the construction period.
Transco upgrade works are expected in the area around Hackins Hey which will close for a weekend on a date to be agreed to minimise impact upon local traffic and businesses.
The whole section of ‘blacktop’ carriageway along Dale Street between the flyover and Exchange St East will be reconstructed before the end of the scheme by Enterprise Liverpool Ltd in partnership with the City Council.
Phase one of work on Old Hall Street, on the footpath outside the Radisson Hotel has been completed. Work is continuing on the opposite footpath in the same location although progress was slowed due to emergency works by Scottish Power in the same location. Work in this section of the street from Leeds Street junction to Old Leeds Street will take approximately another week The initial section of footpath at the entrance of Old hall Street is now complete. Traffic Management will be removed from the junction with Leeds Street at the end of this week and be moved onto the section of footpath between Old Leeds Street and Rigby Street. Transco have been undertaking works at this junction under agreement with the City council to minimize disruption in the future.
The whole of the CCMS works in the Commercial District be completed by early 2011.
For more information on these and other highway schemes, please visit www.liverpool.gov.uk/highwayprojects.
back
The Dale Street work is continuing between Vernon Street and Cheapside with the temporary road closure of Cheapside and Hockenhall Alley allowing the construction of new raised sections of footpath across the side roads along Dale Street.
During this closure, access into Cheapside and Cunliffe Street will still be via Tithebarn Street but egress will be unavailable onto Dale Street making the streets temporarily two-way.
The work area will then move in sections towards Hatton Garden before moving back along the opposite side of the road. The slip road from Hatton Garden will be temporarily closed to allow the safe construction of the kerbs and footpaths.
Delays are continuing to be experienced due to shallow underground services found on site but the City Council is working with partners to undertake diversion works to minimise delays to the construction period.
Transco upgrade works are expected in the area around Hackins Hey which will close for a weekend on a date to be agreed to minimise impact upon local traffic and businesses.
The whole section of ‘blacktop’ carriageway along Dale Street between the flyover and Exchange St East will be reconstructed before the end of the scheme by Enterprise Liverpool Ltd in partnership with the City Council.
Phase one of work on Old Hall Street, on the footpath outside the Radisson Hotel has been completed. Work is continuing on the opposite footpath in the same location although progress was slowed due to emergency works by Scottish Power in the same location. Work in this section of the street from Leeds Street junction to Old Leeds Street will take approximately another week The initial section of footpath at the entrance of Old hall Street is now complete. Traffic Management will be removed from the junction with Leeds Street at the end of this week and be moved onto the section of footpath between Old Leeds Street and Rigby Street. Transco have been undertaking works at this junction under agreement with the City council to minimize disruption in the future.
The whole of the CCMS works in the Commercial District be completed by early 2011.
For more information on these and other highway schemes, please visit www.liverpool.gov.uk/highwayprojects.